Case study · Featured by the Church of England

St James’, Shirley.

From gas heating that had to be switched on hours in advance, to infrared chandeliers and a building that no longer burns any fossil fuels.

Building
St James’, Shirley — a brick parish church and Silver Eco Church
Installer
Electric Heating Solutions
Installed
Infrared chandeliers in the main church, smaller infrared heaters in side rooms
Replaced
A gas-fired heating system
Grants
£23,463 — just under half the project cost
Energy
Green electricity tariff; no fossil fuels used

The challenge.

St James’ cares for creation as part of its mission. It is a Silver Eco Church, and its large churchyard is managed for biodiversity and enjoyed by the local community. The church wanted heating that matched those values better than gas.

The old system was also unreliable. It had to be switched on several hours before a service or event, and even then it did not always warm the church on the coldest days.

The approach.

Deputy Churchwarden Kate Crocker led the project. The church took expert advice from its diocesan Net Zero Carbon Manager and was put forward as a Demonstrator Church for the Church of England’s Net Zero Carbon Programme.

After weighing up the options, the church chose infrared heating. It warms people directly rather than heating the whole volume of air, so a lofty church becomes comfortable quickly.

What was installed.

  • Main church: infrared chandeliers
  • Side rooms and other spaces: smaller infrared heaters
  • Electricity: the church moved to a green tariff, so the building now runs without fossil fuels

The church hall’s heating had already been changed in an earlier, separate project.

Watch the film

Hear it from the church.

Funding.

Two grants covered just under 50% of the project cost:

£13,673Church of England Net Zero Carbon Programme
£9,790The Benefact Trust

The result.

The church now has heating that is more reliable, and chandeliers the congregation finds beautiful.

“There is no worry or anxiety about whether the heating is going to work.”

Linda, Churchwarden, St James’ Shirley

Advice for other churches.

Kate’s message to churches thinking about greener heating is simply to make a start. The Church of England also suggests:

  • Reading its Practical Guide to Net Zero Carbon for Churches
  • Contacting your diocese’s Net Zero Carbon Officer for support
  • Talking to a specialist about the right system for your building — we’re happy to help

Source: “St James’, Shirley is transformed by new heating system”, Church of England, 30 September 2026.

Get in touch

Talk to our team.

Tell us about your building and what you need. We’ll get back to you with advice and a free, no-obligation estimate.

  • NICEIC Qualified technicians
  • ECA Qualified technicians
  • 5–10yr Guarantees and warranties
  • Free Site visit and estimate
Send us a message